BTY Consolidation

BTY Consolidation

An extensive upgrade of the Booster transfer lines took place in LS2 as part of the LIU programme. The programme had as a result the eradication of old control electronics and the installation of new power converters with energy recovery operation.

In the framework of the Accelerators Consolidation Programme the remaining transfer lines, notably the ISOLDE transfer line, is scheduled for consolidation in LS3 of its powering with the same technology of power converters and controls as the rest of the PS Booster transfer lines.

Consolidation Objective  

The consolidation objectives are summarised in the following points:

  • Replace equipment that reached end of life (MIL-1553 controls, powering),
  • Enable energy recovering operation for energy economy,
  • Co-locate powering of magnets located before the ISOLDE separating wall from building 197 to building 361,
  • Guarantee that the new powering solutions will be compatible with a possible upgrade of ISOLDE@2GeV.

The selected power converter technology has been used since 2019 in all of the injector complex transfer lines (TT2, BTL, East Area) hence it is a natural candidate for the ISOLDE transfer lines.

Project Team

EPC Responsible TBD
Team members G. Le Godec, S.Reignier, C. Mutin

Project documentation

Project and quality

Project on EDMS edms folder
Project on INDICO Indico pages
Project on DFS .DFS
Project mandate  
Milestone plan  
EVM Structure  

Project background

Consolidation request .edms
ACC-CONS and HL-LHC projects covering the period LS3-LS4 .edms
   

Technical documents

Magnetic measurement results of the dipole PXMBXFBCWP .edms
Magnetic measurement results of the Q130 quadrupole magnet .edms
   
   

Functional documents

BTY Powering specification .edms
ECR b.197 .edms
ECR b.361-BHP .edms

Procurement documents

   
   
   

Safety related documents

   
   
   

Design

   
   
   

Tests and validation

   
   
   

 

EXTERNAL SERVICES
Electrical Mains Infrastructure Requirements

 

 

Water Cooling Infrastructure Requirements  
Building Floor Infrastructure Requirements  

 

Project Timeline

 The project timeline and milestones

 
 