BTY Consolidation
An extensive upgrade of the Booster transfer lines took place in LS2 as part of the LIU programme. The programme had as a result the eradication of old control electronics and the installation of new power converters with energy recovery operation.
In the framework of the Accelerators Consolidation Programme the remaining transfer lines, notably the ISOLDE transfer line, is scheduled for consolidation in LS3 of its powering with the same technology of power converters and controls as the rest of the PS Booster transfer lines.
Consolidation Objective
The consolidation objectives are summarised in the following points:
- Replace equipment that reached end of life (MIL-1553 controls, powering),
- Enable energy recovering operation for energy economy,
- Co-locate powering of magnets located before the ISOLDE separating wall from building 197 to building 361,
- Guarantee that the new powering solutions will be compatible with a possible upgrade of ISOLDE@2GeV.
The selected power converter technology has been used since 2019 in all of the injector complex transfer lines (TT2, BTL, East Area) hence it is a natural candidate for the ISOLDE transfer lines.
Project Team
| EPC Responsible | TBD |
| Team members | G. Le Godec, S.Reignier, C. Mutin |
Project documentation
Project and quality
| Project on EDMS | edms folder |
| Project on INDICO | Indico pages |
| Project on DFS | .DFS |
| Project mandate | |
| Milestone plan | |
| EVM Structure |
Project background
| Consolidation request | .edms |
| ACC-CONS and HL-LHC projects covering the period LS3-LS4 | .edms |
Technical documents
| Magnetic measurement results of the dipole PXMBXFBCWP | .edms |
| Magnetic measurement results of the Q130 quadrupole magnet | .edms |
Functional documents
| BTY Powering specification | .edms |
| ECR b.197 | .edms |
| ECR b.361-BHP | .edms |
| Work Package Analysis | .edms |
Planning 361
| Preparation of water cooling connections for SIRIS PCs | 26/10/2026 to 20/11/2026 |
| Installation of SIRIUS PCs for Q130 quadrupoles in BTY | 01/04/2027 to 28/06/2027 |
| Installation of AC power (CANALIS) + direct power connection & UPS from ERD4*25A | 03/05/2027 to 02/06/2027 |
| FGC3 BTY SIRIUS (RQF2632804) | 08/07/2027 to 09/07/2027 |
| WIC BTY (RQF2391909) | 05/07/2027 to 16/07/2027 |
| DC cables for quads + SIRIUS PCs (RQF2609590) | 28/10/2027 to 17/11/2027 |
| Sirius power converter maintenance (water must be avaiable!) - end of LS3 | 10/01/2028 to 14/01/2028 |
| Test of new SIRIUS_S PCs for BTY line quadrupoles | 10/01/208 to 28/01/20258 |
Planning for 197
Safety related documents
Design
Tests and validation
| EXTERNAL SERVICES | |
| Electrical Mains Infrastructure Requirements |
|
| Water Cooling Infrastructure Requirements | |
| Building Floor Infrastructure Requirements | |
Project Timeline
The project timeline and milestones